New Construction Notice:

The worldwide shortage of materials and supplies has affected every industry, including the electrical industry, and Heber Light & Power is no exception. While we continue to work to procure materials and supplies in a timely manner, we are currently out of some key items and expect that we will continue to see shortages into the future. Please be aware that while we can evaluate your new construction project request, and design your proposed project, we cannot guarantee the availability of the materials needed for your project. By paying the estimated project cost, you will be added to our wait list for materials. When the materials are available for your project, you will be billed for the additional cost of materials. Once your final payment is received, we will schedule your project for construction.

Instructions for Adding Electric Service

Application & Fee for “Will Serve” Letter
1. Customer Pays $200 fee & submits Will Serve Application
2. HL&P Project Manager evaluates project & responds with a “Will Serve” letter, upon approval
Power Design, Application & Fee
When project is ready for design phase:
1. Pay $300 job initiation fee*
2. Submit Power Design Application and Site Plan via email to building@heberpower.com (send PDF & DWG)

*Each resubmitted project design will be charged an additional $20 per residence for redesign.
Job Evaluation & Line Extension Design
1. HL&P PM conducts site assessment
2. PM completes line extension design
3. PM provides work order # and job invoice
Line Extension
1. Pay Invoice
2. Contractor/Developer installs conduit to HL&P Standards
3. HL&P inspects & completes GPS of conduit prior to back fill.
4. After final inspection, HL&P crew is assigned to complete line extension
Project Design, Application & Fee
When project is ready for design phase:
1. Pay $300 job initiation fee
2. Submit Application and Site Plan via email to building@heberpower.com (send PDF & DWG)
Job Evaluation & Line Extension Design
1. HL&P PM conducts site assessment
2. PM completes line extension design
3. PM provides work order # and job invoice
Line Extension
1. Pay Invoice
2. Contractor/Developer installs conduit to HL&P Standards
3. HL&P inspects & completes GPS of conduit prior to back fill.
4. After final inspection, HL&P crew is assigned to complete line extension
Impact & Meter Fee Payment
1. Pay impact fee & meter charge (fees based on service size).
Temporary Service
1. If needed for construction phase, apply for temporary service using the Electrical Service Application.
Meter Base Inspection & Connection
1. The applicable city or county department will inspect the meter base and provide the approval to HL&P
2. Upon notification of approval, HL&P schedules as serviceman to connect the meter.
error: Content is protected !!

Commercial Electric Service Application Form

* Indicates a Required Field *
If you are moving out of the Heber Light & Power Service area you must contact the
business office at 435-654-1581. 

Safari not supported for form submissions. Please use Chrome, Firefox or Edge browsers.

Thank You


If yes, please provide your previous address.

Customer Information:

Please supply a minimum of two (2) vaid forms of identification:

Residence Information:

Mailing Address - (If different than Service Address):

Responsible Party

Please supply a minimum of two (2) vaid forms of identification:
If Renting the following information is required:

Agreement Information:

 

Residential Electric Service Application Form

* Indicates a Required Field *
If you are moving out of the Heber Light & Power Service area you must contact the
business office at 435-654-1581. 

Safari is not supported for form submissions. Please use Chrome, Firefox or Edge browsers.

Thank You


If yes, please provide your previous address.

Customer Information:

Please supply a minimum of two (2) vaid forms of identification:
Employer Information:

Residence Information:

Mailing Address - (If different than Service Address):

Applicant's Spouse/Roommate Information:

Please supply a minimum of two (2) vaid forms of identification:

Agreement Information:

 
Search